Page 1 of 1

titles of completed tasks crossed out

Posted: Mon Mar 17, 2014 3:49 pm
by CyberCrone
Why are titles of completed tasks crossed out? It is already obvious they are completed with check in checkbox. I can't find anything in styles to change this. How can I change to NOT cross out titles of completed tasks?

Re: titles of completed tasks crossed out

Posted: Mon Mar 17, 2014 4:53 pm
by Tester
I don't work with tasks but I assume that this is the way to change it:

- Tools ---> Options ---> Tasks & Reminders
- Uncheck the box at "Strikeout completed tasks" [by default the box is checked]
- Click on OK

Image

Re: titles of completed tasks crossed out

Posted: Mon Mar 17, 2014 8:54 pm
by CyberCrone
Tester wrote:I don't work with tasks but I assume that this is the way to change it:

- Tools ---> Options ---> Tasks & Reminders
- Uncheck the box at "Strikeout completed tasks" [by default the box is checked]
- Click on OK
Another DUH! I had forgotten about formatting in Options. Thanks again!